NovaTuff offers a standard 5 year material warranty. This warranty is renewable with recoating, extending the life of the fountain for many years. A labor warranty is available for an additional fee when installed by a qualified applicator.
Group: NovaTuff Tank and Fountain Coatings FAQ’s
NovaTuff reaches its full cure after 7 days at 80 degrees F. It can typically be walked on after 24 hours and filled with water at 3 days. Pool chemicals should not be introduced until coating is fully cured.
Proper preparation is the most important part of any coating project. NovaTuff provides detailed installation guides and concrete preparation guides, which are available on the NovaTuff website or from your local NovaTuff retailer. Prime a concrete fountain with 2 coats of NovaTuff P-505 Epoxy Primer at 1 gallon per 150 […]
Yes, use 2 coats of NovaTuff P-505 Epoxy Primer at 1 gallon per 150 to 200 square feet. Concrete must be more than 28 days old. The concrete may outgas with the first coat but the second coat will complete the seal. If temperatures are high, it can be better […]
Cracks larger than 1/8 inch should be routed out and filled with caulk. Smaller static cracks can be coated.
Once installed, NovaTuff can handle temperature extremes, from below freezing to high desert temperatures. It should be installed when temperatures are above 40 degrees F and rising with no freeze in the immediate forecast.